An Israeli startup is developing contactless electromagnetic acceleration for hypersonic testing and future orbital cargo logistics. Public evidence includes financing, a laboratory demonstration report and an Alaska study agreement.

TechnologySpace launch
ScopeAdjacent
EnergyNot published
Endurance disclosureNot applicable
Dated events10 · 2025 to 2026
EvidenceHigh confidencereviewed 2026-09-25

The 100 m/s figure comes from a secondary report of laboratory progress, and 8 km/s is a target for a future orbital system. The MOU doesn't mean a launcher has been built in Alaska. The investor and the agency describe the financing differently, so it's recorded as the $12m announced, without adding the pre-seed again.

Caesarea Industrial ParkLocality-level placement from the stated site · 32.48, 34.93

Dated record on a timeline

202320242025202620272028202920302023-08: Founder concept presented to investor2024: Company founded2025-12-01: Company emerges with funding disclosure2025-12-01: Caesarea accelerator construction reported2025-12-01: Preliminary logistics agreements disclosed2026-04-15: Alaska Aerospace MOU announced2026-04-22: Alaska site remains undecided2026-04-27: Laboratory-launch progress reported2027: Initial accelerator revenue target2030: Approximate space-access ambition202320242025202620272028202920302023-08: Founder concept presented to investor2024: Company founded2025-12-01: Company emerges with funding disclosure2025-12-01: Caesarea accelerator construction reported2025-12-01: Preliminary logistics agreements disclosed2026-04-15: Alaska Aerospace MOU announced2026-04-22: Alaska site remains undecided2026-04-27: Laboratory-launch progress reported2027: Initial accelerator revenue target2030: Approximate space-access ambition
test or operationalannouncement, contract, delivery, funding, agreement, terminationpublicationplanned or proposed

Event mix

Publication 1Announcement 4Funding 1Agreement 2Planned 2

The public record is mostly publications and announcements. Tests are the minority in almost every program.

Reported energy

0.11 MJ10 MJ33 MJ record0.11 MJ10 MJ33 MJ record

No energy figure in the reviewed sources. Stored, charging and muzzle energy are different quantities and are never merged. The 33 MJ reference is the Dahlgren record shot of 10 December 2010.

Endurance disclosure

Not applicable

Rail-contact service life doesn't apply to contactless coil-based acceleration. Future coil and system data belong in a broader endurance-disclosure field.

Dated record 10 events · event date shown, not report date

  1. AnnouncementFounder concept presented to investor

    Angular Ventures dates receipt of the initial pitch to August 2023.

    The August 2023 activity was disclosed retrospectively in December 2025.

    primary evidence
  2. AnnouncementCompany founded

    Israel Space Agency reports 2024 formation.

    primary evidence
  3. FundingCompany emerges with funding disclosure

    Agency reports $12m raised including a $1m Innovation Authority grant.

    primary evidence
  4. AnnouncementCaesarea accelerator construction reported

    Agency describes miniature accelerator under construction for hypersonic testing.

    primary evidence
  5. AgreementPreliminary logistics agreements disclosed

    D-Orbit and Orbit Fab agreements reported.

    Disclosure date; actual signing dates unspecified.

    primary evidence
  6. AgreementAlaska Aerospace MOU announced

    Parties agree to explore next-generation launch activity in Alaska.

    primary evidence
  7. AnnouncementAlaska site remains undecided

    AAC CEO tells KMXT that Poker Flat is under consideration.

    No completed Moonshot facility is documented at the prospective site.

    secondary evidence
  8. PublicationLaboratory-launch progress reported

    Globes reports recent launches at 100 m/s.

    Publication date only; event occurred earlier, exact date unknown.

    secondary evidence
  9. PlannedInitial accelerator revenue target

    Investor anticipates revenue from initial accelerator if plans succeed.

    The date is a commercial target whose achievement remains to be confirmed.

    primary evidence
  10. PlannedApproximate space-access ambition

    December 2025 interview describes reaching space in roughly five years, dependent on funding.

    The approximate year 2030 is derived from a relative aspiration; a mission date has yet to be established.

    primary evidence

Sources 7