Three-phase Italian research project, a2021.010, considering inert projectile and small space-payload launch. Phase 1 concluded positively; phase 2 awarded to Kairospace.
Orbital launch is a research objective. Procurement documents give no completed orbital launch, energy figure or verified firing site.
Dated record on a timeline
Event mix
The public record is mostly publications and announcements. Tests are the minority in almost every program.
Reported energy
No energy figure in the reviewed sources. Stored, charging and muzzle energy are different quantities and are never merged. The 33 MJ reference is the Dahlgren record shot of 10 December 2010.
Endurance disclosure
Not published in reviewed sources
No quantified same-rail endurance found in reviewed sources.
Dated record 5 events · event date shown, not report date
- ContractHERAKLES phase 1 procurement authorized
Ministry decision covers first of three phases with Kairospace.
primary evidence - ContractHERAKLES phase 1 contract signed
Ministry procurement page identifies contract 2147.
primary evidence - ContractHERAKLES phase 2 procurement authorized
Ministry approves proceeding with second phase after successful phase 1.
primary evidence - FundingHERAKLES phase 2 budget amended
Revised financial profile schedules public payments in 2026 and 2027.
primary evidence - ContractHERAKLES phase 2 award notice published
Kairospace award listed at EUR 691,865.54 excluding VAT, with a 12-month execution term.
It's the publication date only, so an exact completion date can't be calculated from it.
primary evidence
Sources 5
- HERAKLES phase 1 determination to contractItalian Ministry of Defence · 2023-02-09 · primary
- HERAKLES phase 2 procurement pageItalian Ministry of Defence · 2025-06-27 · primary
- HERAKLES phase 2 determination to contract 2025-095Italian Ministry of Defence · 2025-06-27 · primary
- HERAKLES phase 2 amendment 2025-197Italian Ministry of Defence · 2025-11-24 · primary
- HERAKLES phase 2 contract award resultsItalian Ministry of Defence · 2026-02-16 · primary
Record EU-P09. A working source link does not mean that every statement on the linked page is accurate. Each source is cited only for the claim it supports. Reviewed 2026-09-25.